In today’s connected world, reliable high-speed internet is no longer a luxury — it’s a necessity for modern communities. At the same time, designing and deploying a fiber network has become increasingly complex and time-intensive. Waiting too long to begin the search for a provider — or delaying vendor selection until less than 12 months out — can lead to unnecessary stress, rushed decisions, or even a gap in service for your community. Below is a recommended timeline to help you plan ahead and set your community up for success.

Ideal timeline to select a service provider and begin transition

21 MONTHS OUT

Poll residents

Determine most important features necessary in potential bulk agreement

24 MONTHS OUT

Build committee or select designated board members to head solicitation
process of new broadband provider

Begin conducting research on new broadband provider options

Review current contract. When does it expire? Are there non-renewal elements to consider?

14 MONTHS OUT

Contract negotiations with top two vendors

18 MONTHS OUT

Collect and evaluate proposals

Presentations from vendors

12 MONTHS OUT

Communicate selected partner to residents and notify of upcoming construction process

Begin construction

13 MONTHS OUT

Contract signed with selected partner

Estimated schedule received

2 MONTHS OUT

Installation and activation

Resident is proficient in using services

3 MONTHS OUT

Marketing process begins

Resident learns details on products and services available

Resident schedules installation

POST-LIVE DATE

Maintenance as usual

Regular communication to residents

LIVE DATE

All residents have had installation opportunity and are actively using services

Download the PDF